Speedier clearances no magic wand for India's infrastructure logjam

By Matthias Williams and Manoj Kumar

NEW DELHI (Reuters) - Scrambling for remedies as investors' faith in India sagged, the government said last week it fast-tracked approval for a slew of infrastructure projects worth $28 billion: but the stroke of a pen in New Delhi will not be enough.

The government hopes that speeding up the launch of hundreds of new power plants, highways and oil exploration blocks will breathe new life into an economy that has fallen off its perch as an emerging market high-flier.

Growth in the latest quarter was the slowest since during the global financial crisis, and the rupee has tumbled ever deeper against the U.S. dollar. Failing to get the projects off the ground would be another blow.

However, there is no evidence to suggest that these projects will somehow sidestep the obstacles that have hobbled construction for years - from red tape and land acquisition battles to banks' unwillingness to lend to a risk-prone sector.

Only a quarter of infrastructure projects are completed on time in the country, according to a 2012 report by Ernst & Young consultants.

Financing will be one of the biggest challenges right now. The infrastructure sector is one of the biggest contributors to banks' growing bad loans, with outstanding debt of about $120 billion, and tight liquidity conditions mean debt-laden companies will find it tough to raise fresh funds.

"These new measures are much too wonderful to be true," said Eric Mookherjee, a Paris-based fund manager at Shanti India, which manages Indian stocks worth more than $300 million, including IRB Infrastructure Developers Ltd .

"Expediting approvals for the projects that were stalled for years is not going to start the machines from tomorrow morning," he said. "The issue with infrastructure in India is financing, and if liquidity is going to be sucked out of the market to support the rupee it will be very hard for the banks to fund these projects."

GRAPHIC: Infrastructure plan http://r.reuters.com/dab72v

HOOPS AND HURDLES

Anil Swarup, a senior official in the prime minister's office who heads a group that monitors and helps steer projects already cleared, said no companies had complained to his group of a lack of progress. However, he accepted that a fast-tracked project still faced many hurdles, including wrangles over land acquisition and law-and-order problems at a state level.

"We cannot expect an overnight transformation," he said. "In any project, there would be a number of issues and ... until those are resolved, the project does not go on stream."

One beneficiary of last week's project clearances by a cabinet panel was Essar Group, a diversified conglomerate with interests in power, oil and steel. After a 5-year wait, Essar was finally promised environmental approval to develop two coal blocks that will feed a power plant in the state of Jharkhand.

The reaction of one company official, though, was lukewarm. The approval may have come through, but a timeline for when the company can actually start mining was still uncertain.

"Funding is linked to the environment clearance to the coal blocks, and banks will release funds once we have all the clearances. The announcement is a positive development, but we have got nothing in our hands, so we will progress on this once everything has been approved," said the official.

SHIVERING RUPEE

India's track record for infrastructure development is miserable compared with China and most emerging market economies, and its failure on this score has sapped growth.

The government has targeted spending of $1 trillion on new projects over the five years to 2017, but it has fallen short of previous funding and implementation goals, and much of the country is still plagued by power blackouts and bumpy roads.

A land acquisition bill, which is aimed at speeding up infrastructure and industrial projects by giving farmers better compensation for selling their land, was passed in the lower house of parliament on Thursday.

It takes about 295 days to acquire or lease public land in India, more than twice the global average, Standard Chartered wrote in a research note on Friday that cited World Bank data. Getting private land takes 99 days, versus a global average of 61 days.

Despite New Delhi's best efforts to get infrastructure moving, the problem appears to be getting worse. The percentage of total projects delayed on account of land acquisition-related issues more than trebled to 11.3 percent as of March 2013 from six years ago, the note said.

"How can you run through these projects when land must be acquired before financial closure?" said a senior official at the Planning Commission on clearances. "You can't talk things up. Look at the rupee, it's shivering."

The Federation of Indian Chambers of Commerce and Industry was scathing about the bill, which will replace colonial-era legislation, saying that not only will land cost more, the process of acquiring it will be stretched by 4-5 years.

STOPPING THE ROT

The government's Cabinet Committee on Investment (CCI), set up by Prime Minister Manmohan Singh in January, was charged with stopping the rot by solving inter-departmental disputes and speeding up clearances, especially environment and fuel permits.

Among its successes, the committee ended a 14-year saga involving NTPC Ltd , the country's largest power producer, and Coal India Ltd , the world's biggest coal miner, over the construction of a 1,980 MW power project.

NTPC was initially granted permission to build the plant in Jharkhand, but then Coal India claimed the site after coal reserves were discovered underneath it. After years of dispute and the establishment of a committee headed by a top civil servant to look into the case, the CCI ruled in favour of NTPC.

However, NTPC still had more hoops to jump through before it could finally issue equipment tenders. It had to move the construction site by about 300 metres, and because environmental clearances had expired they had to be obtained again.

Such hurdles are typical in India, where the average project needs 56 separate permissions that can take two years to obtain.

Vinayak Chatterjee, head of the Feedback Infra consultancy, said the clearances were a positive step, but resistance from ministries keen to guard their veto rights has watered down the CCI's powers.

"The CCI was originally conceived as a National Investment Board ... and that was supposed to be a far more powerful body which would have been empowered to give clearances," he said. "The CCI does not have statutory powers to override line ministries. So effectively it has become a pressure and coordinating body."

"I think the line ministries felt uncomfortable about their powers being taken away, as usual," he said, referring to those ministries in the line of approvals needed for such projects.

For example, the committee can take a decision to nudge Coal India to provide fuel for a power project, but it cannot force the miner to do so, or stipulate a timeline for the supplies, an official at a major infrastructure group said.

"While the CCI has cleared the projects, there is no clear uptick in activity related to such projects," Barclays said in a June research note. "We believe that activity/investment related to such projects could remain subdued, given the weak momentum and sentiment in the economy - that is, the CCI clearance, per se, is not the 'game changer' the government sees it as being."

(Additional reporting by Sumeet Chatterjee in MUMBAI and by Sanjeev Miglani in NEW DELHI; Editing by John Chalmers and Ian Geoghegan)

Matches

MORE TOP STORIES TODAY

Pietersen to miss Delhi's first game

Pietersen to miss Delhi's first game

The former England batsman will have to wait lead the franchise as he is out of the match against Bangalore with a finger injury. More »

Kallis, Narine star in Knight Riders’ crushing win

Kallis, Narine star in Knight Riders’ crushing win

An all-round display saw Knight Riders thump Mumbai Indians by 41 runs in the IPL-7 opener. More »

Gavaskar wants a clean IPL

Gavaskar wants a clean IPL

"Integrity is non-negotiable..." says the BCCI's interim chief ahead of Season 7 of the tainted league. More »

'Yak' Kallis still on top of his game

'Yak' Kallis still on top of his game

The 38-year-old South African veteran turned it on for Kolkata Knight RIders in the opening match of IPL-7. More »

Srinivasan named in fixing report: SC

Srinivasan named in fixing report: SC

The court emphasised that the tainted administrator can no longer work for the BCCI. More »

Yuvraj happy to play for RCB: Kohli

Yuvraj happy to play for RCB: Kohli

New-look RCB will play their first game of IPL-7 on Thursday. More »

IPL: News Line

IPL: News Line

A round-up of all the news from this season of the IPL. More »

Shane Watson issues moral warning

Shane Watson issues moral warning

'Everyone knows what is right and what is wrong and if you do the wrong thing it will be found out' More »

Why I'm not looking forward to the IPL

Why I'm not looking forward to the IPL

Welcome to another season of a league that many watch but few trust. More »

Nepal players call off boycott

Nepal players call off boycott

Thaw in relations after formation of an advisory committee that would work in tandem with the Cricket Association of Nepal. More »

Johnson may quit T20s for Tests

Johnson may quit T20s for Tests

Australia's Mitchell Johnson may quit limited-overs cricket to prolong his test career with an eye on the 2015 Ashes series in England, the fast bowler… More »

There's a lot going on: Fleming

There's a lot going on: Fleming

He experienced anxious moments in the lead-up to the tournament as the courts decided on whether to suspend the franchise, he said, but stressed that the… More »

Latif couldn’t work with tainted players

Latif couldn’t work with tainted players

Former Pakistan cricket captain Rashid Latif said Tuesday he turned down the job of national chief selector because he could not work with ex-players tainted… More »

We are not over-confident: Bailey

We are not over-confident: Bailey

Indian Premier League — George Bailey-led Kings XI Punjab will face Chennai Super Kings on Friday. More »

Big runs expected, with bat and ball

Big runs expected, with bat and ball

Royal Challengers Bangalore: Their main concern, once again, is the fast bowling More »

Taxing issue — BCCI hits roadblock

Taxing issue — BCCI hits roadblock

MoU between BCCI & its units to avoid double taxation delayed after a few decline to share details. More »

Black Caps pick rookie duo for West Indies

Black Caps pick rookie duo for West Indies

New Zealand selectors included two new caps in a 15-man Test squad named Tuesday to tour the West Indies, with injury-hit spinner Dan Vettori's future… More »

The stage is set for IPL-7 to start

The stage is set for IPL-7 to start

The Preview — Defending champions Mumbai Indians take on Kolkata Knight Riders More »

Srinivasan appeals to court to allow BCCI comeback

Srinivasan appeals to court to allow BCCI comeback

He was aggrieved by the allegations against him during the hearing. More »

Klinger on his exit from South Australia

Klinger on his exit from South Australia

Michael Klinger has revealed he felt compelled to leave South Australia after being told he would be only a fringe part of the Redbacks' plans for next season, and disputed the suggestion that he left… More »

India: cricket's Brazil

India: cricket's Brazil

They are tough to beat with a big talent base exposed to good facilities. (CYCSPL) More »

Delhi Daredevils say no to gifts

Delhi Daredevils say no to gifts

Franchises are doing their bit to refurbish the image of the tainted league. More »

India-Pakistan Test series likely in 2015

India-Pakistan Test series likely in 2015

The revival of Indo-Pak Test ties could take place in UAE. More »

Kohli hopes to end RCB trophy drought

Kohli hopes to end RCB trophy drought

'This time around we will hope to go few more steps ahead and actually get that trophy' More »